Transfer test infrastructure
Purpose
After project closure, tests are conducted during the utilization and maintenance phase for corrections and for further developments. For that reason, the test infrastructure including the test concept must be transferred to the core organization.
Basic idea
To enable maintenance and further development of the system during the utilization phase after the end of the project, the test infrastructure including the test concept must be transferred to the core organization before project closure.
HERMES-specific
The test concept and test infrastructure are transferred after acceptance, but before project closure. They are transferred by the project organization to those responsible for operation and further development at the user, developer, and operator.
Basis/prerequisites
Activities
-
Adjust the test concept with test case descriptions and test data or update it with findings from the tests.
-
Inform and train those responsible.
-
Carry out formal transfer.
-
Record transfer in the minutes.
Outcomes
Relationships
Module | Task | Task responsibility | Outcome | Involved in creation of outcome |
---|