Lessons learned

Description

The lessons learned are documented. They support the continual improvement process in the project and in the core organization. They provide valuable information for the further course of the project and for subsequent projects by adopting positive aspects and, if possible, preventing negative ones.

Content

  1. Contact
  2. Subject area
  3. Date
  4. Lessons learned: positive/negative
  5. Relevance: possible significance for own project or other projects
  6. Recommendation: information for the core organization

Templates

Relationships