Conduct test
Purpose
Tests are conducted to ensure that the system meets the stipulated requirements. The tests are carried out and the test results are evaluated and recorded.
Basic idea
Provided that the preconditions for doing so are met, the first tests are carried out on the test system. Accordingly, the test infrastructure must have been realized beforehand.
HERMES-specific
The conduct test task comprises:
-
proper testing on the test system of the realized test infrastructure;
-
testing of the integrated system as part of the integrate the system into operation task;
-
testing the realized product as part of the realize product task;
-
testing the realized migration procedure as part of the realize migration procedure task; and
-
quality testing as part of the perform quality assurance task.
The tests are carried out according to the test case descriptions in the test concept. They are further specified as needed. The test results entered in the test report are evaluated according to criteria defined in the test concept. The test report is checked before the decision on preliminary acceptance.
As needed, the tests are repeated several times until the quality criteria are met. Open issues from the tests and the next steps in this regard are established by binding agreement. The test plan in the test concept is continually updated.
Basis/prerequisites
Activities
-
Check whether the preliminary conditions for testing are met to start the tests.
-
Perform tests according to the test concept.
-
Log the test results and evaluate them according to criteria in the test concept.
-
If necessary, correct defects and repeat tests.
-
Agree on how to deal with unresolved issues.
Outcomes
Relationships
Module | Task | Task responsibility | Outcome | Involved in creation of outcome |
---|---|---|---|---|
Tests | Conduct test | Test manager | Test report | Test manager , Tester |
Test concept | Test manager , Tester, User representative , Operations manager , Business analyst, Developer |