Decide on call for tenders
Purpose
The decision on call for tenders creates the prerequisite for publication.
Basic idea
After the decision on call for tenders, the tender documentation is published or, in the case of an invitation procedure, sent out.
HERMES-specific
The decision on call for tenders is made by the project sponsor, where applicable with the involvement of the body in charge of tenders in the core organization. The project sponsor ensures coordination with the core organization.
Basis/prerequisites
Activities
-
Add further criteria to the tender checklist.
-
Check the tender documentation with the tender checklist.
-
Check whether overarching strategies, standards, and specifications have been adhered to and whether confirmations from the competent bodies are available.
-
Coordinate the decision with the core organization.
-
Make formal decision on call for tenders.
Outcomes
Relationships
Module | Task | Task responsibility | Outcome | Involved in creation of outcome |
---|---|---|---|---|
Procurement | Decide on call for tenders | Project sponsor | Tender checklist | Project sponsor, Project management, User representative , Quality and risk manager |
Tender milestone | Project sponsor, Project management, Project committee, User representative | |||
List of steering project decisions | Project sponsor, Project management |