Skip to main content

Work order

Description

The work order contains all relevant information for completing a set task. The project manager uses it to give orders to the project staff within the framework of project planning, management, information, and monitoring. Work orders can be issued internally or externally. Any solution-specific orders must be coordinated with the user representative in advance.

Content

  • Work objectives
  • Outcomes
  • Boundaries
  • Prerequisites and dependencies
  • List of activities with
    • Reference to the outcomes
    • Activity
    • Those responsible/involved
    • Plan hours
    • Deadlines
    • Status
  • Resource requirements
  • Presentation of outcomes
  • Quality assurance

Relationships

Outcomes